Comparative Evaluation of Conventional and Modular Formwork Systems Through a Cost Time Decision Making Framework

Comparative Evaluation of Conventional and Modular Formwork Systems Through a Cost Time Decision Making Framework

Authors

DOI:

https://doi.org/10.56741/jnest.v5i03.2525

Keywords:

4D BIM, 5D BIM, Break-Even Analysis, Conventional Formwork, Decision-Making Framework, Life Cycle Cost Analysis, Modular Formwork

Abstract

Formwork costs can account for 20–25% of total construction costs, making the selection of an appropriate formwork system an important aspect of improving cost and time efficiency in multi-story building projects. This study employed a comparative descriptive approach based on Building Information Modeling (BIM) simulation and Life Cycle Cost Analysis (LCCA) to compare the time and cost performance of conventional and modular formwork systems for the beam, column, and slab elements of Building X, a 9-story reinforced concrete building in East Java. A 3D BIM model was developed in Autodesk Revit to extract structural volumes, which were converted into formwork areas and then analyzed using productivity coefficients from SNI 7394:2008 and the AHSP of the Ministry of Public Works and Housing (PUPR) for time analysis (4D BIM), budget plan (RAB) unit prices for cost analysis (5D BIM), and a gate-to-gate LCCA complemented by Break-Even Analysis (BEA). Modular formwork achieved a time efficiency of 50.35% and an initial cost efficiency of 20.59%, with a total life cycle cost 68.65% more economical. The BEA results show that modular formwork becomes more economical starting from the third use cycle, with reuse cost as the most dominant parameter, contributing 89.25% of the difference in total LCC. The evaluation framework based on 4D–5D BIM integrated with LCCA and BEA proved effective as a structured, data-driven decision-making framework for formwork system selection in multi-story building projects.

Downloads

Download data is not yet available.

Author Biographies

Dhena Arthamevia, Universitas Brawijaya

is a master's student in the Department of Civil Engineering Faculty of Engineering, Universitas Brawijaya, Malang 65145, Indonesia. Her research focuses on formwork systems, and life cycle cost analysis in construction management. (email: dhena.arthamevia@gmail.com).

Lilya Susanti, Universitas Brawijaya

is a lecturer and researcher in the Department of Civil Engineering, Faculty of Engineering, Universitas Brawijaya, Malang 65145, Indonesia. She specializes in Structural Engineering, with research interests in structural mechanics and material engineering innovation relevant to reinforced concrete construction. (email: lilya_st@ub.ac.id).

Yatnanta Padma Devia, Universitas Brawijaya

is the Head of the Master Program and a researcher in the Department of Civil Engineering, Faculty of Engineering, Universitas Brawijaya, Malang 65145, Indonesia. She specializes in Construction Management, with research interests in sustainable construction, construction demolition waste, and green building. (email: yatnanta@ub.ac.id).

References

Badan Standardisasi Nasional (BSN), SNI 2847:2019: Persyaratan Beton Struktural untuk Bangunan Gedung dan Penjelasan, Jakarta: BSN, 2019.

Bappenas, Rencana Pembangunan Jangka Menengah Nasional (RPJMN) 2025–2029, Jakarta, 2025.

T. Terzioglu, G. Polat, and H. Turkoglu, “Formwork system selection criteria for building construction projects: A structural equation modelling approach,” Buildings, vol. 12, no. 2, e204, Feb. 2022, doi: 10.3390/buildings12020204.

A. S. Supriyono, I. N. D. P. Putra, and B. Trigunarsyah, “Comparative analysis of formwork systems: Cost efficiency and time management in construction projects,” Adv. Sustainable Sci. Eng. Technol., vol. 7, no. 2, e0250204Feb. 2025, doi: 10.26877/asset.v7i2.1320.

E. Agriansyah, A. Suryo, and E. Arifi, “Selection of methods of carrying out floor plate Bekesting Work with cost comparison,” Appl. Res. Civil Eng. Environ. (ARCEE), vol. 05, no. 01, pp. 14–23, 2024, doi: 10.32722/arcee.v5i01.5753

Badan Standardisasi Nasional (BSN), SNI 7394:2008: Tata Cara Perhitungan Harga Satuan Perkerjaan Beton untuk Konstruksi Bangunan Gedung dan Perumahan, Jakarta: BSN, 2008.

R. Baskova, A. Tazikova, Z. Strukova, M. Kozlovska, and J. Cabala, “A dynamic model for effective and optimal planning of formwork in construction projects,” Buildings, vol. 13, no. 7, e1794, Jul. 2023, doi: 10.3390/buildings13071794.

V. Rajeshkumar, S. Anandaraj, V. Kavinkumar, and K. S. Elango, “Analysis of factors influencing formwork material selection in construction buildings,” Mater. Today Proc., vol. 37, pp. 880–885, Jan. 2021, doi: 10.1016/J.MATPR.2020.06.044.

M. T. Al-Ashwal, R. Abdullah, and R. Zakaria, “Traditional formwork system sustainability performance: Experts’ opinion,” IOP Conf. Series: Materials Sci. Eng., Dec. 2017. doi: 10.1088/1757-899X/271/1/012108.

M. S. Gaddam and A. Achuthan, “A comparative study on newly emerging type of formwork systems with conventional type of form work systems,” Mater. Today Proc., vol. 33, pp. 736–740, Jan. 2020, doi: 10.1016/J.MATPR.2020.06.090.

J. Nilimaa, Y. Gamil, and V. Zhaka, “Formwork engineering for sustainable concrete construction,” CivilEng, vol. 4, no. 4, pp. 1098–1120, Dec. 2023, doi: 10.3390/civileng4040060.

Kementerian Perkerjaan Umum dan Perumahan Rakyat (PUPR), Peraturan Menteri PUPR no. 22/PRT/M/2018 tentang Pembangunan Gedung Negara, Jakarta, 2018.

I. U. Rehman, K. M. Mazher, and I. Y. Wuni, “Systematic review of 4D BIM benefits in construction projects,” Results in Eng., e107091, 2025, doi: 10.1016/j.rineng.2025.107091.

Q. Lu, J. Won, and J. C. P. Cheng, “A financial decision making framework for construction projects based on 5D Building Information Modeling (BIM),” Int. J. Project Manag., vol. 34, no. 1, pp. 3–21, Jan. 2016, doi: 10.1016/j.ijproman.2015.09.004.

U. Haider, U. Khan, A. Nazir, and M. Humayon, “Cost comparison of a building project by manual and BIM,” Civil Eng. J. (Iran), vol. 6, no. 1, pp. 34–49, Jan. 2020, doi: 10.28991/cej-2020-03091451.

S. K. Fuller and S. R. Petersen, “Life-cycle costing manual for the federal energy management program,” NIST Handbook 135, National Institute of Standards and Technology, Gaithersburg, MD, 1995. doi: 10.6028//NISHT.HB.135-1995.

Stanford University, Guidelines For Life Cycle Cost Analysis, 2005.

R. Sacks, C. M. Eastman, G. Lee, and P. M. Teicholz, BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers, 3rd ed, Hoboken, NJ, USA: John Wiley & Sons, 2018.

M. S. Raza, B. A. Tayeh, Y. I. Abu Aisheh, and A. M. Maglad, “Potential features of building information modeling (BIM) for application of project management knowledge areas in the construction industry,” Heliyon, vol. 9, no. 9, Sep. 2023, doi: 10.1016/j.heliyon.2023.e19697.

J. Lee, Y. J. Park, C. H. Choi, and C. H. Han, “BIM-assisted labor productivity measurement method for structural formwork,” Autom. Constr., vol. 84, pp. 121–132, Dec. 2017, doi: 10.1016/j.autcon.2017.08.009.

B. Yoo, H. Yoon, Y. Kim, and K. M. Lee, “Stepwise application of BIM-based parametric modeling to tapered slip-form system,” in Procedia Eng., pp. 112–119, 2016, doi: 10.1016/j.proeng.2016.04.028.

W. N. F. A. W. A. Basir, U. Ujang, and Z. Majid, “Adaptation 4D and 5D BIM for BIM/GIS data integration in construction project management,” in IOP Conf. Series: Earth and Environ. Sci., vol. 1274, no. 1, e012002, 2023, doi: 10.1088/1755-1315/1274/1/012002.

A. W. Hammad, A. Akbarnezhad, P. Wu, X. Wang, and A. Haddad, “Building information modelling-based framework to contrast conventional and modular construction methods through selected sustainability factors,” J. Clean. Prod., vol. 228, pp. 1264–1281, Aug. 2019, doi: 10.1016/J.JCLEPRO.2019.04.150.

N. Y. Huwaida, F. S. Handayani, and M. Rifai, “Perbandingan biaya dan waktu antara metode konvensional dengan metode modular menggunakan Microsoft project,” J. Ris. Rekayasa Sipil, vol. 8, no. 1, pp. 18-26, 2024. doi: 10.20961/jrrs.v8i1.95314.

R. Yogiswara, A. Andreas, and R. T. Lestari, “Analisis faktor penyebab keterlambatan dan perbandingan pekerjaan pemasangan bekisting aluminium-bekisting konvensional ditinjau dari segi waktu, biaya, dan mutu: Studi kasus proyek Oyama Plaza Apartemen dan Hotel Jakarta,” J. Artesis, vol. 3, no. 1, pp. 49-61, 2023, doi: 10.35814/artesis.v3i1.5022.

C. Khosakitchalert, N. Yabuki, and T. Fukuda, “Automatic concrete formwork quantity takeoff using building information modeling,” in The 19th Int. Conf. on Construction Appl. of Virtual Reality Bangkok, Thailand, pp. 21-28, 2019. [Online]. Available: https://www.researchgate.net/publication/337286106_Automatic_Concrete_Formwork_Quantity_Takeoff_Using_Building_Information_Modeling

C. Hyun, C. Jin, Z. Shen, and H. Kim, “Automated optimization of formwork design through spatial analysis in building information modeling,” Autom. Constr., vol. 95, pp. 193–205, Nov. 2018, doi: 10.1016/J.AUTCON.2018.07.023.

D. Mansuri, D. Chakraborty, H. Elzarka, A. Deshpande, and T. Gronseth, “Building information modeling enabled cascading formwork management tool,” Autom. Constr., vol. 83, pp. 259–272, Nov. 2017, doi: 10.1016/J.AUTCON.2017.08.016.

R. L. Peurifoy and G. D. Oberlender, Formwork for Concrete Structures 4th ed., New York, NY. USA: McGraw-Hill,” 2011.

P. Pishdad and I. O. Onungwa, “Analysis of 5d BIM for cost estimation, cost control, and payments,” J. Inf. Technol. Construct., vol. 29, pp. 525–548, 2024, doi: 10.36680/j.itcon.2024.024.

Buildings and constructed assets - Service life planning - Part 5: Life-cycle costing ISO 15686-5, 2017. [Online]. Available: https://www.iso.org/standard/61148.html

M. A. Musarat, W. S. Alaloul, M. S. Liew, A. Maqsoom, and A. H. Qureshi, “Investigating the impact of inflation on building materials prices in construction industry,” J. Building Eng., vol. 32, e101485, Nov. 2020, doi: 10.1016/J.JOBE.2020.101485.

T. Terzioglu and G. Polat, “Formwork system selection in building construction projects using an integrated rough AHP-EDAS approach: A case study,” Buildings, vol. 12, no. 8, e1084, Aug. 2022, doi: 10.3390/buildings12081084.

R. Saavedra, W. Meléndez, and G. Garcés, “Comparative analysis of quantity take-off in concrete, steel bars and formwork in apartment buildings based on cad and BIM methodologies,” J. Inf. Technol. Construct., vol. 30, pp. 159–184, 2025, doi: 10.36680/j.itcon.2025.008.

A. Monteiro and J. P. Martins, “A survey on modeling guidelines for quantity takeoff-oriented BIM-based design,” Autom. Constr., vol. 35, pp. 238–253, 2013, doi: 10.1016/j.autcon.2013.05.005.

D. Olsen and J. M. Taylor, “Quantity take-off using Building Information Modeling (BIM), and its limiting factors,” Procedia Eng., vol. 196, pp. 1098–1105, Jan. 2017, doi: 10.1016/J.PROENG.2017.08.067.

S. A. Vassen, “Impact of BIM-based quantity take off for accuracy of cost estimation,” Int. J. Construct. Eng. Manag., vol. 2021, no. 3, pp. 55–69, 2021, doi: 10.5923/j.ijcem.20211003.01.

N. A. Haron, I. S. Hassim, Mohd. R. Abd. Kadir, and Mohd S. Jaafar, “Building cost comparison between conventional and formwork system: A case study of four-storey school buildings in Malaysia,” Am. J. Appl. Sci., vol. 2, no. 4, pp. 819–823, 2005, doi: 10.3844/ajassp.2005.819.823.

M. D. V. Lawdy, E. Arifi, M. N. Wijaya, B. Krisnawan, and T. Rochman, “On the methodology of conventional and semi-system formwork project comparison,” MethodsX, vol. 13, Dec. 2024, doi: 10.1016/j.mex.2024.102824.

A. T. Balasbaneh, W. Sher, and M. H. W. Ibrahim, “Life cycle assessment and economic analysis of Reusable formwork materials considering the circular economy,” Ain Shams Eng. J., vol. 15, no. 4, Apr. 2024, doi: 10.1016/j.asej.2023.102585.

M. Altaf, W. S. Alaloul, M. A. Musarat, and A. H. Qureshi, “Life cycle cost analysis (LCCA) of construction projects: sustainability perspective,” Environ. Dev. Sustain., vol. 25, no. 11, pp. 12071–12118, Nov. 01, 2023, Springer Science and Business Media B.V. doi: 10.1007/s10668-022-02579-x.

M. Altaf, R. Jaffari, W. S. Alalaoul, M. A. Musarat, and S. Ammad, “Developing automated strategy of life cycle cost analysis (LCCA) with building information modeling (BIM) integration for building projects,” Results in Eng., vol. 25, Mar. 2025, doi: 10.1016/j.rineng.2025.104179.

A. B. Putra, D. O. I. Putra, G. A. Sentosa, and R. A. Saputra, “Cost analysis and method comparison on high-rise building column formworks by three formwork methods,” IOP Conf. Series: Earth Environ. Sci., vol. 1324, no. 1, e012007, 2024, doi: 10.1088/1755-1315/1324/1/012007.

Z. Mei, M. Xu, H. Li, Z. Huang, and S. Luo, “Cooperation mode for concrete formwork reuse among construction sites,” Sustain. Cities Soc., vol. 95, e104584, Aug. 2023, doi: 10.1016/J.SCS.2023.104584.