Critical Supply Chain Risks in Modular Construction: Assessment of Cost, Time, and Quality Impacts
DOI:
https://doi.org/10.56741/jnest.v5i03.2573Keywords:
Modular Construction, Supply Chain Risk Management, Severity Index, State-Owned Enterprise ContractorAbstract
Modular Integrated Construction (MiC) offers opportunities to improve construction cost and time efficiency, but its implementation depends on supply chain readiness. In Indonesia, dependence on imported materials and an underdeveloped modular ecosystem complicate adoption amid substantial housing shortages. Previous studies have rarely distinguished supply chain risks affecting cost, time, and quality or examined state-owned enterprise (SOE) contractors as early MiC adopters. This study assessed these risks using practitioner perspectives from five SOE contractors in Jakarta. Thirty practitioners completed a questionnaire covering 37 risks across seven categories. Of these, 36 met validity and reliability requirements, with Cronbach's alpha values ranging from 0.955 to 0.982. Risk severity was evaluated using the Severity Index (SI) and classified through a Probability-Impact Matrix (PIM). Most risks were categorized as moderate. Four risks were classified as high: long distances between project sites and modular factories (LG3) for cost; inadequate assembly planning and scheduling (DP3) and delayed owner payments (PG3) for time; and delayed module installation (IM5) for quality. The findings highlight the importance of coordinated planning, contract management, and supply chain collaboration. Contractors should strengthen scheduling and stakeholder coordination, while module providers should improve production capacity, technical support, quality control, and workforce competencies. The study is limited by its Jakarta-based SOE sample and reliance on perceived risks. Future research should involve broader regional samples, quantify actual cost and schedule impacts, and examine risk relationships using observed project performance data to support more reliable modular construction implementation.
Downloads
References
I. Y. Wuni and G. Q. P. Shen, “Risks identification and allocation in the supply chain of modular integrated construction (MiC),” Modul. Offsite Constr. Summit Proc., pp. 189–197, 2019, doi: 10.29173/mocs93.
N. Bertram, S. Fuchs, J. Mischke, R. Palter G. Strube, and J. Woetzel, Modular Construction: From Projects to Products. McKinsey & Company, 2019.
M. Zohourian, A. Pamidimukkala, S. Kermanshachi, and D. Almaskati, “Modular construction: A comprehensive review,” Buildings, vol. 15, no. 12, pp. 1–21, 2025, doi: 10.3390/buildings15122020.
Y. Zhang, G. Q. Shen, and J. Xue, “A bibliometric analysis of supply chain management within modular integrated construction in complex project management,” Buildings, vol. 14, no. 6, 2024, doi: 10.3390/buildings14061667.
Badan Pusat Statistik, “Backlog Perumahan dan Capaian Penyediaan Perumahan di Indonesia , 2025 – Semester I 2026,” 2026. [Online]. Available: https://www.bps.go.id/id/pressrelease/2026/08/31/2651/backlog-perumahan-mengalami-penurunan-dengan-backlog-1-tercatat-sebesar-12-39-persen-dan-backlog-2-sebesar-24-03-persen-pada-tahun-2026.html
O. Turbaningsih, U. Mutaharah, and P. Saputra, “The study of potential application of modular construction in the development of Indonesia’s new capital city,” J. Tek. Sipil, vol. 29, no. 3, pp. 207-216, 2022, doi: 10.5614/jts.2022.29.3.1.
O. Akinradewo, C. Aigbavboa, D. Aghimien, and A. Oke, “Modular method of construction in developing countries: the underlying challenges,” Int. J. Constr. Manag., vol. 23, no. 8, pp. 1344–1354, 2021, doi: 10.1080/15623599.2021.1970300.
M. J. Ding and F. Jie, “Mitigating the supply chain uncertainties and risks in the construction projects: Case studies of Australian construction projects,” Clean. Logist. Supply Chain, vol. 16, e100237, 2025, doi: 10.1016/j.clscn.2025.100237.
H. Pervez, Y. Ali, D. Pamucar, M. Garai-Fodor, and Á. Csiszárik-Kocsir, “Evaluation of critical risk factors in the implementation of modular construction,” PLoS One, vol. 17, no. 8, e0272448, 2022, doi: 10.1371/journal.pone.0272448.
I. Y. Wuni, G. Q. Shen, and R. Osei-kyei, “Modelling the critical risk factors for modular integrated construction projects,” Int. J. Constr. Manag., vol. 22, no. 11, pp. 2013–2026, 2022, doi: 10.1080/15623599.2020.1763049.
H. Arshad and T. Zayed, “Critical influencing factors of supply chain management for modular integrated construction,” Autom. Constr., vol. 144, e104612, 2022, doi: 10.1016/j.autcon.2022.104612.
I. Y. Wuni and G. Q. Shen, “Exploring the critical production risk factors for modular integrated construction projects,” J. Facil. Manag., vol. 21, no. 1, pp. 50–68, 2023, doi: 10.1108/JFM-03-2021-0029.
M. Hussein, A. E. E. Eltoukhy, A. Karam, and I. A. Shaban, “Modelling in off-site construction supply chain management: A review and future directions for sustainable modular integrated construction,” J. Clean. Prod., vol. 310, e127503, 2021, doi: 10.1016/j.jclepro.2021.127503.
D. A. Alqahtani, M. Ahmed, J. Mallick, and M. D. S. Al Shahrani, “Integrated risk priority assessment of engineering and non-engineering factors influencing Saudi Arabian construction projects,” Buildings, vol. 16, e1518, 2026, doi: 10.3390/buildings16081518.
S. Husin, F. Fachrurrazi, M. Rizalihadi, and M. Mubarak, “Implementing Fuzzy TOPSIS on project risk variable ranking,” Adv. Civ. Eng., vol. 2019, e9283409, 2019, doi: 10.1155/2019/9283409.
I. Y. Wuni, G. Q. Shen, and A. B. Saka, “Computing the severities of critical onsite assembly risk factors for modular integrated construction projects,” Eng. Constr. Archit. Manag., vol. 30, no. 5, pp. 1864–1882, 2023, doi: 10.1108/ECAM-07-2021-0630.
N. Nizarli, A. Abdullah, Y. Away, and I. Mahdar, “Multi-stakeholder priorities for modular construction adoption under uncertainty: An analytic hierarchy process and Monte Carlo analysis in Aceh , Indonesia,” Sustainability, vol. 17, no. 23, e10487, 2025, doi: 10.3390/su172310487.
A. A. Khan, R. Yu, T. Liu, N. Gu, and J. Walsh, “Volumetric modular construction risks: A comprehensive review and digital-technology-coupled circular mitigation strategies,” Sustain., vol. 15, no. 8, e7019, 2023, doi: 10.3390/su15087019.
Q. Cai, Y. Du, and R. Wang, “Analysis on supply chain risk factors of prefabricated buildings using AHP-DEMATEL-ISM model,” Teh. Vjesn., vol. 30, no. 5, pp. 1379–1386, 2023, doi: 10.17559/TV-20230508000614.
H. X. Li, M. Al-Hussein, Z. Lei, and Z. Ajweh, “Risk identification and assessment of modular construction utilizing fuzzy analytic hierarchy process (AHP) and simulation,” Can. J. Civ. Eng., vol. 40, no. 12, pp. 1184–1195, 2013, doi: 10.1139/cjce-2013-0013.
L. Wang, Y. Cheng, and Y. Zhang, “Exploring the risk propagation mechanisms of supply chain for prefabricated building projects,” J. Build. Eng., vol. 74, e106771, 2023, doi: 10.1016/j.jobe.2023.106771.
H. T. Pham, T. Pham, H. Truong Quang, and C. N. Dang, “Supply chain risk management research in construction: A systematic review,” Int. J. Constr. Manag., vol. 23, no. 11, pp. 1945–1955, 2023, doi: 10.1080/15623599.2022.2029677.
I. Y. Wuni, G. Q. P. Shen, and A. T. Mahmud, “Critical risk factors in the application of modular integrated construction: a systematic review,” Int. J. Constr. Manag., vol. 22, no. 2, pp. 133–147, 2022, doi: 10.1080/15623599.2019.1613212.
M. Xia, L. Zhao, and L. Zhao, “A comprehensive risk-assessment method for prefabricated buildings using EPC: A case study from China,” Sustain., vol. 14, no. 3, e1910, 2022, doi: 10.3390/su14031910.
S. Chai, M. Liu, Z. Zhang, and S. Li, “Study on risk identification and key risks of prefabricated building supply chain based on grounded theory,” E3S Web Conf., vol. 275, e3076, 2021, doi: 10.1051/e3sconf/202127503076.
L. Luo, Y. Li, X. Wang, X. Jin, and Z. Qin, “Supply chain vulnerability in prefabricated building projects and digital mitigation technologies,” IEEE Trans. Eng. Manag., vol. 71, pp. 10686–10698, 2024, doi: 10.1109/TEM.2023.3272585.
I. Y. Wuni, G. Q. Shen, and B. G. Hwang, “Risks of modular integrated construction: A review and future research directions,” Front. Eng. Manag., vol. 7, no. 1, pp. 63–80, 2020, doi: 10.1007/s42524-019-0059-7.
A. O. Bello, A. A. Khan, A. Idris, and H. M. Awwal, “Barriers to modular construction systems implementation in developing countries’ architecture, engineering and construction industry,” Eng. Constr. Archit. Manag., vol. 31, no. 8, pp. 3148–3164, 2024, doi: 10.1108/ECAM-10-2022-1001.
Y. Mei, “Research on supply chain risk of prefabricated building based on AHP Model,” in ICMSEM, 2024, pp. 1038–1046. doi: 10.2991/978-94-6463-256-9_102.
A. Sharafat, K. Latif, and J. Seo, “Risk analysis of TBM tunneling projects based on generic bow-tie risk analysis approach in difficult ground conditions,” Tunn. Undergr. Sp. Technol. Inc. Trenchless Technol. Res., vol. 111, e103860, 2021, doi: 10.1016/j.tust.2021.103860.
Y. O. L. Tobing, D. P. Sari, and P. A. Wicaksono, “Analisis risiko proyek konstruksi dengan importance index dan bowtie analysis,” Ind. Eng. Online J., vol. 7, no. 4, 2012. [Online]. Available: https://ejournal3.undip.ac.id/index.php/ieoj/article/view/23004/21044%0A
A. R. Zaidan, K. Soeryodarundio, and S. Setiono, “Analisis manajemen risiko proyek dengan metode Severity Index (SI) pada proyek pembangunan gedung X Kota Surakarta,” Globe Publ. Ilmu Tek. Teknol. Kebumian, Ilmu Perkapalan, vol. 2, no. 3, pp. 211–221, 2024, doi: 10.61132/globe.v2i3.501.
Elfrianto, Panduan Lengkap Analisis Statistik dalam Penelitian, First Edit. Medan: UMSU Press, 2025. [Online]. Available: http://umsupress.umsu.ac.id/
S. Widodo, L. Festy, and A. La Ode, Buku Ajar Metodologi Penelitian, 1st ed. Pangkalpinang: CV Science Techno Direct, 2023.
L. Reginancy, M. Purba, G. Budianto, and N. Raya, “Analysis of material supply chain risk weight using severity index method,” J. Inov. Teknol. dan Rekayasa, vol. 9, no. 2, pp. 551–557, 2024, doi: 10.31572/inotera.Vol9.Iss2.2024.ID423.
H. A.Rani, Manajemen Risiko Proyek, 1 st edit. Yogyakarta, Indonesia: Deepublish, 2025.
C. Li, “Little’s test of missing completely at random,” Stata J., vol. 13, no. 4, pp. 795–809, 2013, doi: 10.1177/1536867X1301300407.
F. M. Kikhia, “A study on evaluation of mean and median imputation methods and their impact on statistical analysis of missing data,” Sirte Univ. Sci. J., vol. 14, no. 2, pp. 57–64, 2024, doi: 10.37375/susj.v14i2.3090.
I. Y. Wuni, G. Q. Shen, and M. F. Antwi-afari, “Exploring the design risk factors for modular integrated construction projects,” Constr. Innov., vol. 23, no. 1, pp. 213–228, 2023, doi: 10.1108/CI-02-2021-0025.
E. M. A. C. Sandeepani, T.A.S., Ekanayake and I. Ashayeri, “Modelling design stage risks in modular integrated construction in Sri Lanka,” 2023, no. 21-22 July, pp. 821–832. doi: 10.31705/WCS.2023.66.
L. Keda and Z. Weiwei, “Study on risk assessment of prefabricated construction supply chain based on AHP,” in E3S Web of Conferences, 2021, vol. 275, e3083. doi: 10.1051/e3sconf/202127503083.
A. O. Bello, K. S. Ihedigbo, T. Bello, and H. M. Awwal, “Implementation strategies for modular construction systems in developing countries: Perspectives of Nigerian AEC professionals,” J. Sustain. Environ., vol. 2, no. 2, pp. 106–114, 2023, doi: 10.3126/josem.v2i2.55203.
M. Assaf, M. Hussein, B. T. Alsulami, and T. Zayed, “A mixed review of cash flow modeling: Potential of blockchain for modular construction,” Buildings, vol. 12, no. 12, p. 2054, 2022, doi: 10.3390/buildings12122054.
A. Gurmu, F. F. Tafti, A. Mills, and J. Kite, “Defects in modular building construction: A systematic lifecycle review and implications for sustainable delivery,” Sustainability, vol. 18, no. 8, e4000, 2026, doi: 10.3390/su18084000.
Downloads
Published
How to Cite
Issue
Section
Categories
License
Copyright (c) 2026 Journal of Novel Engineering Science and Technology

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.