Bridging Internal Constraints and Performance: A SEM-PLS Analysis of Public Infrastructure Projects in the Buton Islands
DOI:
https://doi.org/10.56741/jnest.v4i03.1263Keywords:
Construction Management, Project Performance, Infrastructure Delivery, Developing Regions, Site Supervision, Planning SystemsAbstract
Public infrastructure projects in developing regions often face performance issues due to internal capacity gaps and weak management systems. This study emphasizes both the direct and mediating effects of internal factors on project outcomes, with stronger justification for using SEM-PLS and additional comparative methods. Regression-based robustness checks and PLSpredict cross-validation are incorporated to validate the results. The research investigates the mediating role of construction management in linking internal organizational factors to project performance in the Buton Islands, Southeast Sulawesi. Key elements examined include planning quality, supervisory practices, communication effectiveness, and equipment readiness, measured against cost, time, and quality outcomes. A quantitative design using Structural Equation Modeling with Partial Least Squares (SEM-PLS) was applied to data from 54 construction professionals in government and private sectors. To address statistical concerns with the small sample size and many indicators, redundant items were eliminated (loading < 0.70), and discriminant validity was tested using HTMT ratios. Findings indicate that internal organizational conditions have a moderate but significant direct effect on project performance, while this influence is substantially strengthened when mediated by effective construction management. Novelty is underscored by situating the analysis in the Buton Islands, a geographically isolated and resource-constrained region rarely studied in international literature, extending systems theory and the Iron Triangle to new environments. The strongest predictive paths involve budgeting systems, scheduling mechanisms, and quality assurance frameworks. Beyond technical dimensions, managerial practices also foster institutional trust and resilience, offering practical guidance for policymakers and practitioners.
Downloads
References
A. A. Seman, H. M. S. Ahmed, A. Ahmed, and A. A. Haso, “Causes and Effects of Project Delay in Public Construction Projects in Ethiopia,” 2023, doi: 10.21203/rs.3.rs-2680680/v1. DOI: https://doi.org/10.21203/rs.3.rs-2680680/v1
Y. A. Lawal and O. G. Hammed, “Critical Success Factors for Public Sector Projects in Lagos,” Organization and Human Capital Development, vol. 2, no. 1, pp. 66–77, 2023, doi: 10.31098/orcadev.v2i1.1341. DOI: https://doi.org/10.31098/orcadev.v2i1.1341
J. Jupir, K. . Aziz, and H. Hassan, “Determinants of Successful Collaborative Project Management: Insights From Malaysian Construction Industry,” International Journal of Technology, vol. 14, no. 6, p. 1344, 2023, doi: 10.14716/ijtech.v14i6.6651. DOI: https://doi.org/10.14716/ijtech.v14i6.6651
Z. Lubis, “The Importance of Communication Management Improving the Performance of Construction Project Managers in Developing Countries,” Journal of Southwest Jiaotong University, vol. 56, no. 3, pp. 473–484, 2021, doi: 10.35741/issn.0258-2724.56.3.40. DOI: https://doi.org/10.35741/issn.0258-2724.56.3.40
W. A. Ola-awo, A. Alayande, G. O. Bashir, and L. O. Oyewobi, “Critical Success Factors for Effective Internal Construction Stakeholder Management in Nigeria,” Acta Structilia, vol. 28, no. 1, pp. 1–31, 2021, doi: 10.18820/24150487/as28i1.1. DOI: https://doi.org/10.18820/24150487/as28i1.1
T. Wang, E. K. Owusu, Q. He, Z. Tian, and D. Wu, “Empirical Assessments of the Determinants of Construction Megaprojects’ Success: Evidence From China,” Sustainability, vol. 14, no. 22, p. 14730, 2022, doi: 10.3390/su142214730. DOI: https://doi.org/10.3390/su142214730
R. Karimi, M. B. Shishehgarkhaneh, R. C. Moehler, and Y. Fang, “Exploring the Impact of Social Media Use on Team Feedback and Team Performance in Construction Projects: A Systematic Literature Review,” Buildings, vol. 14, no. 2, p. 528, 2024, doi: 10.3390/buildings14020528. DOI: https://doi.org/10.3390/buildings14020528
S. H. Khahro, H. H. Shaikh, N. Y. Zainun, B. Sultan, and Q. H. Khahro, “Delay in Decision-Making Affecting Construction Projects: A Sustainable Decision-Making Model for Mega Projects,” Sustainability, vol. 15, no. 7, p. 5872, 2023, doi: 10.3390/su15075872. DOI: https://doi.org/10.3390/su15075872
T. Omotayo, J. Ross, A. K. Oyetunji, and C. Udeaja, “Systems Thinking Interplay Between Project Complexities, Stakeholder Engagement, and Social Dynamics Roles in Influencing Construction Project Outcomes,” Sage Open, vol. 14, no. 2, 2024, doi: 10.1177/21582440241255872. DOI: https://doi.org/10.1177/21582440241255872
K. Ssenyange, “The Impact of Leadership Styles on Government Construction Project Success: A Structural Equation Modelling Approach,” Ijfirm, vol. 13, no. Issue 3, pp. 50–75, 2023, doi: 10.35808/ijfirm/363. DOI: https://doi.org/10.35808/ijfirm/363
K. Ssenyange and K. Chodokufa, “The Mediation Role of Stakeholders’ Engagement in Enhancing Public Construction Projects Success – The Case of Uganda,” European Project Management Journal, vol. 14, no. 2, pp. 78–91, 2024, doi: 10.56889/gbec3568. DOI: https://doi.org/10.56889/gbec3568
M. Ali, S. Rehman, and Q. Abdul, “Fulfilling Stakeholder Needs and Concerns: A Path to Satisfaction in Construction Projects,” vol. 17, pp. 73–80, 2025, doi: 10.4028/p-5rmm6f. DOI: https://doi.org/10.4028/p-5RMm6F
R. Dwivedi and P. Dwivedi, “Role of Stakeholders in Project Success: Theoretical Background and Approach,” Ijfirm, vol. 11, no. Issue 1, pp. 38–49, 2021, doi: 10.35808/ijfirm/248. DOI: https://doi.org/10.35808/ijfirm/248
I. G. Mwangi and J. M. Kisimbi, “Critical Success Factors Influencing the Performance of Infrastructure Projects in the Aviation Industry in Kenya; A Case of Moi International Airport,” Journal of Entrepreneurship and Project Management, vol. 5, no. 2, pp. 93–113, 2020, doi: 10.47941/jepm.498. DOI: https://doi.org/10.47941/jepm.498
A. Rani, R. Singh, S. Taneja, A. B. Prasad, and S. Dhiman, “A Review on Key Performance Indicators for Measuring Real Estate Project Success,” International Journal of Sustainable Development and Planning, vol. 16, no. 4, pp. 791–800, 2021, doi: 10.18280/ijsdp.160420.
H. Ghaleb and A. A. Abdullah, “A Conceptual Framework for Impact of Project Complexity on Success of Railway Construction Projects: The Moderating Role of Effective Communications to All Stakeholders,” The Journal of Management Theory and Practice (Jmtp), vol. 2, no. 1, pp. 62–69, 2021, doi: 10.37231/jmtp.2021.2.1.85. DOI: https://doi.org/10.37231/jmtp.2021.2.1.85
M. Mojidra, Prof. D. J.R.Pitroda, P. S. Shah, and J. R. Gohil, “The Impact of Stakeholder Communication and Coordination on Project Outcome,” Interantional Journal of Scientific Research in Engineering and Management, vol. 08, no. 11, pp. 1–7, 2024, doi: 10.55041/ijsrem39215. DOI: https://doi.org/10.55041/IJSREM39215
A. B. Adhi and F. Muslim, “Development of Stakeholder Engagement Strategies to Improve Sustainable Construction Implementation Based on Lean Construction Principles in Indonesia,” Sustainability, vol. 15, no. 7, p. 6053, 2023, doi: 10.3390/su15076053. DOI: https://doi.org/10.3390/su15076053
P. W. A. H. Lawanga and Y. G. Sandanayake, “Lean Design Management Practices Associated With Stakeholder Management During Pre-Construction Stage in Sri Lanka,” pp. 392–402, 2021, doi: 10.31705/wcs.2021.34. DOI: https://doi.org/10.31705/WCS.2021.34
T. A. Ghuzdewan, A. Nugroho, and H. Priyosulistyo, “Evaluating the Interrelationships Among Key Stakeholders’ Performance in Achieving Project Success,” International Journal of Sustainable Development and Planning, vol. 18, no. 1, pp. 193–200, 2023, doi: 10.18280/ijsdp.180120. DOI: https://doi.org/10.18280/ijsdp.180120
J. Węgrzyn and A. Wojewnik‐Filipkowska, “Stakeholder Analysis and Their Attitude Towards PPP Success,” Sustainability, vol. 14, no. 3, p. 1570, 2022, doi: 10.3390/su14031570. DOI: https://doi.org/10.3390/su14031570
A. M. Farouk et al., “Performance Indicators for Assessing Environmental Management Plan Implementation in Water Projects,” Sustainability, vol. 16, no. 8, p. 3146, 2024, doi: 10.3390/su16083146. DOI: https://doi.org/10.3390/su16083146
E. A. Herbertson, G. O. Makinde, B. H. Akinlabi, A. O. shonubi, and A. O. Ebose, “The Dimensional Effect of Optimal Project Risk Management Practices on Project Quality of Selected Construction Companies in Nigeria,” International Journal of Innovative Research in Education Technology & Social Strategies, vol. 10, no. 2, pp. 79–98, 2023, doi: 10.48028/iiprds/ijiretss.v10.i2.08. DOI: https://doi.org/10.48028/iiprds/ijiretss.v10.i2.08
J. F. Hair, G. T. M. Hult, C. M. Ringle, and M. Sarstedt, A primer on partial least squares structural equation modeling (PLS-SEM), 3rd ed. Thousand Oaks, CA: Sage Publications, 2021. DOI: https://doi.org/10.1007/978-3-030-80519-7
T. Anjamrooz, S. El-Sayegh, and L. Romdhane, “Key Portfolio Selection Criteria for Sustainable Construction,” Buildings, vol. 14, no. 6, p. 1777, 2024, doi: 10.3390/buildings14061777. DOI: https://doi.org/10.3390/buildings14061777
A. N. I. Perdana and I. P. A. Wiguna, “Indicators Analysis of Scope Creep Causation Factors in Indonesian Offshore Oil &Amp; Gas Construction Projects,” Journal of Green Science and Technology, vol. 8, no. 2, 2024, doi: 10.33603/jgst.v8i2.9181. DOI: https://doi.org/10.33603/jgst.v8i2.9181
M. A. A. Alahdal, M. N. A. Rahman, and N. A. Mosali, “Successful Renewable Energy Implementation Model,” International Journal of Sustainable Construction Engineering Technology, vol. 13, no. 2, 2022, doi: 10.30880/ijscet.2022.13.02.008. DOI: https://doi.org/10.30880/ijscet.2022.13.02.008
M. Ghanbari, “Assessing the Accident-Cost Relationship in Building Construction Projects Using Structural Equation Modeling,” Jordan Journal of Civil Engineering, vol. 18, no. 1, 2024, doi: 10.14525/jjce.v18i1.02. DOI: https://doi.org/10.14525/JJCE.v18i1.02
M. Lorko, M. Servátka, and L. Zhang, “Hidden Inefficiency: Strategic Inflation of Project Schedules,” SSRN Electronic Journal, 2020, doi: 10.2139/ssrn.3695879. DOI: https://doi.org/10.2139/ssrn.3695879
Q. Zhang and S. Hao, “Construction Project Manager’s Emotional Intelligence and Team Effectiveness: The Mediating Role of Team Cohesion and the Moderating Effect of Time,” Front Psychol, vol. 13, 2022, doi: 10.3389/fpsyg.2022.845791. DOI: https://doi.org/10.3389/fpsyg.2022.845791
J. Konior and M. Szóstak, “Methodology of Planning the Course of the Cumulative Cost Curve in Construction Projects,” Sustainability, vol. 12, no. 6, p. 2347, 2020, doi: 10.3390/su12062347. DOI: https://doi.org/10.3390/su12062347
Z. Malaeb, M. ElMenshawy, A. Badreddine, O. Azakir, and F. Hamzeh, “A Fuzzy Framework for Contractor Selection on IPD Projects,” 2023, doi: 10.24928/2023/0107. DOI: https://doi.org/10.24928/2023/0107
R. Hasan, S. A. Chowdhury, and J. Akter, “Construction Project Monitoring: The Cost and Schedule Control by Earned Value Method (EVM),” Journal of Technology Management and Business, vol. 8, no. 1, 2021, doi: 10.30880/jtmb.2021.08.01.001. DOI: https://doi.org/10.30880/jtmb.2021.08.01.001
S. Lu and M. Pamadi, “Performance Analysis System Using Earned Value Method for Electrical Greenhouse Work Project in Batam City,” Jurnal Indonesia Sosial Teknologi, vol. 4, no. 12, pp. 2288–2296, 2023, doi: 10.59141/jist.v4i12.828. DOI: https://doi.org/10.59141/jist.v4i12.828
J. Jufriza, Y. R. Alkhaly, and A. Jalil, “Optimizing Road Pavement Projects Through Earned Value Concepts,” International Journal of Engineering Science and Information Technology, vol. 4, no. 4, pp. 187–196, 2024, doi: 10.52088/ijesty.v4i4.602. DOI: https://doi.org/10.52088/ijesty.v4i4.602
G. Cataldo, E. Qian, and J. Auclair, “Multifidelity Uncertainty Quantification and Model Validation of Large-Scale Multidisciplinary Systems,” J Astron Telesc Instrum Syst, vol. 8, no. 03, 2022, doi: 10.1117/1.jatis.8.3.038001. DOI: https://doi.org/10.1117/1.JATIS.8.3.038001
A. Hussein and S. F. Moradinia, “Time and Cost Management in Water Resources Projects Utilizing the Earned Value Method,” Journal of Studies in Science and Engineering, vol. 4, no. 1, pp. 91–111, 2024, doi: 10.53898/josse2024417. DOI: https://doi.org/10.53898/josse2024417
M. A. MOIRORE and Y. W. Muchelule, “Project Schedule Management on Performance of Construction Projects in Mombasa County, Kenya,” strategicjournals.com, vol. 10, no. 2, 2023, doi: 10.61426/sjbcm.v10i2.2624. DOI: https://doi.org/10.61426/sjbcm.v10i2.2624
J. Gomes and M. Rom�ão, “Aligning Project and Benefits Management With Balanced Scorecard Approach to Achieve Project Success,” Journal of Business Ecosystems, vol. 4, no. 1, pp. 1–11, 2023, doi: 10.4018/jbe.320481. DOI: https://doi.org/10.4018/JBE.320481
S. Şenses and M. Kumral, “Trade-Off Between Time and Cost in Project Planning: A Simulation-Based Optimization Approach,” Simulation, vol. 100, no. 2, pp. 127–143, 2023, doi: 10.1177/00375497231196889. DOI: https://doi.org/10.1177/00375497231196889
D. W. Chan and D. Aghimien, “Bolstering Measures for Combating the Challenges of Safe Working Cycle Implementation in Hong Kong’s Construction Industry,” Sustainability, vol. 14, no. 7, p. 3772, 2022, doi: 10.3390/su14073772. DOI: https://doi.org/10.3390/su14073772
T. S. Nguyen and S. Mohamed, “Interactive Effects of Agile Response-to-Change and Project Complexity on Project Performance,” pp. 311–320, 2020, doi: 10.1007/978-981-15-1910-9_26. DOI: https://doi.org/10.1007/978-981-15-1910-9_26
N. Nigar, M. K. Shahzad, S. Islam, O. Oki, and J. M. Lukose, “Multi-Objective Dynamic Software Project Scheduling: A Novel Approach to Handle Employee’s Addition,” Ieee Access, vol. 11, pp. 39792–39806, 2023, doi: 10.1109/access.2023.3265716. DOI: https://doi.org/10.1109/ACCESS.2023.3265716
A. Rani, R. Singh, S. Taneja, A. B. Prasad, and S. Dhiman, “A Review on Key Performance Indicators for Measuring Real Estate Project Success,” International Journal of Sustainable Development and Planning, vol. 16, no. 4, pp. 791–800, 2021, doi: 10.18280/ijsdp.160420. DOI: https://doi.org/10.18280/ijsdp.160420
S. A. Banihashemi and M. Khalilzadeh, “Time-Cost-Quality-Environmental Impact Trade-Off Resource-Constrained Project Scheduling Problem With DEA Approach,” Engineering Construction & Architectural Management, vol. 28, no. 7, pp. 1979–2004, 2020, doi: 10.1108/ecam-05-2020-0350. DOI: https://doi.org/10.1108/ECAM-05-2020-0350
A. Vázquez, I. Pozzana, G. Kalogridis, and C. Ellinas, “Activity Networks Determine Project Performance,” Sci Rep, vol. 13, no. 1, 2023, doi: 10.1038/s41598-022-27180-0. DOI: https://doi.org/10.1038/s41598-022-27180-0
E. Safapour, K. Sharareh, and A. Jafari, “Effective Project Management Principles and Strategies in Transportation Infrastructure Projects,” pp. 126–135, 2020, doi: 10.3311/ccc2020-064. DOI: https://doi.org/10.3311/CCC2020-064
A. Nouh, E.-S. El-Kasaby, and K. Aboulata, “Development of a Prediction System for Design Defects of Buildings,” Civil Engineering Journal, vol. 9, pp. 217–235, 2023, doi: 10.28991/cej-sp2023-09-017. DOI: https://doi.org/10.28991/CEJ-SP2023-09-017
M. Muneer et al., “A Quantitative Study of the Impact of Organizational Culture, Communication Management, and Clarity in Project Scope on Constructions’ Project Success With Moderating Role of Project Manager’s Competencies to Enhance Constructions Management Practices,” Buildings, vol. 12, no. 11, p. 1856, 2022, doi: 10.3390/buildings12111856. DOI: https://doi.org/10.3390/buildings12111856
M. Y. Al-Kuhail, H. A. Al-Dafiry, T. A. H. Barakat, and A. Al-Ansi, “Developing a Diamond Framework Model Based on ‘Integration’ of Project Success Measures for Construction Project Management in Yemen,” Pertanika J Sci Technol, vol. 29, no. 3, 2021, doi: 10.47836/pjst.29.3.23. DOI: https://doi.org/10.47836/pjst.29.3.23
M. Zavari and M. R. Afshar, “The Role of Site Manager Transformational Leadership in the Construction Project Success,” International Journal of Building Pathology and Adaptation, vol. 41, no. 5, pp. 1067–1085, 2021, doi: 10.1108/ijbpa-07-2021-0094. DOI: https://doi.org/10.1108/IJBPA-07-2021-0094
J. E. Latupeirissa, I. L. K. Wong, and H. C. P. Tiyow, “Integration of Parties in the Supply Chain System for the Construction Project Successful Execution,” Journal of Southwest Jiaotong University, vol. 55, no. 5, 2020, doi: 10.35741/issn.0258-2724.55.5.13. DOI: https://doi.org/10.35741/issn.0258-2724.55.5.13
Downloads
Published
How to Cite
Issue
Section
Categories
License
Copyright (c) 2025 Journal of Novel Engineering Science and Technology

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.